PROJECT DESCRIPTION
                           

Client: Lauth Construction
Project: Baldwyn & Lyons, Inc. headquarters
General Contractor: Lauth Construction
Floor Area: 100,000 sf

PROJECT APPROACH


Design/Build

PROJECT SOLUTION

Restoring The Congressional Building as the new headquarters for transportation insurance firm Baldwin & Lyons required a complete renovation of the HVAC system.

EFS demolished all old ducting and VAV boxes, installed new economizer air system throughout the building, replaced chillers, and replaced chiller pumps and piping. We also installed and programmed a new Direct Digital Control (DDC) system.

The project involved massive rigging and hole cutting to supply conditioned air to each floor of the building. Providing relief airflow to maintain proper building pressure also was a challenging of this project.